P0770 The contractual right to a panel of three arbitrators may not be altered by the court, so the arbitrations of disputes arising under one contract that called for arbitration by a panel of three and another contract that called for a single arbitrator should not have been combined and sent to a single arbitrator, and the resulting award should not have been confirmed.CitationPARKER v MCCAW (Consolidated Arbitration) 125 CA4 1494 [See: CCP 1281.3; Gordon v G.R.O.U.P. 49 CA4 998, T/AT 11/96; Vandenberg v Superior Court 21 C4 815, T/AT 10/99]
|
|