P1145 An administrative proceeding brought by a contractor under the Public Contracts Code in which a subcontractor on a public works project was substituted on the ground the subcontractor was substantially delaying or disrupting progress did not have issue preclusion (i.e., collateral estoppel) effect in a subsequent action by the contractor against the subcontractor for breach of contract.CitationKEMP v TITAN (Subcontractor Substitution) 146 CA4 1474 [See: Pacific Lumber v State 37 C4 921] |
|
|
|||||
|
|||||